  • 5851 Nathan Benderson Cir Sarasota, FL, 34235, USA - Sarasota County
    Continually being told no path required from small west lake to rest of park. Approved construction plans show asphalt path. This approved construction plan was to be completed in 5 years. This permit has expired and numerous outstanding items are left incomplete. Time County enforced the requirements with SANCA or Benderson Development.
  • Nathan Benderson Park 5851 Nathan Benderson Cir, Sarasota, FL, 34235, USA - Sarasota County
    Construction roll off dumpsters overflowing with trash bags trash on park island. No construction in park. Code requires commercial dumpsters to have lids, be in a walled enclosure, be properly marked, be emptied with contract hauler and be on an approved county site and development plan.
  • 5851 Nathan Benderson Cir Sarasota, FL, 34235, USA - Sarasota County
    Triple wide trailer approved for temporary use for WRC in Oct 2017 is still on site on island. No site and development approval exist for the trailer. No TUP exists for the trailer. No County water and sewer connection fees of over $5,000 were paid for the utility connection. No fire or EMS impacts were paid for the trailer. It exists occupied by 8-10 persons daily in violation of land development and building code. Does not meet ADA.