Last Fall Ethan Allen Parkway had extensive work done. By the time it was completed it was too late to pave it properly. No where do we see if there are any plans to have it paved correctly. Looking for some answers.
Last Fall Ethan Allen Parkway had extensive work done. By the time it was completed it was too late to pave it properly. No where do we see if there are any plans to have it paved correctly. Looking for some answers.
4 Comments
Acknowledged DPW Pine Customer Service (Verified Official)
Closed DPW Engineering AT (Verified Official)
Due to the water relining and upgrades done on Ethan Allen Parkway. It was never planned to be fully paved until 2019. Ethan Allen Parkway is still planned to be paved this coming summer and you can access the Burlington Construction Portal to stay up to date on all activities and construction around the city. www.burlingtonvt.gov/construction
The Department of Public Works has resolved this request. Thanks for helping to keep Burlington a great place to live and work.
Reopened iloathepotholes (Registered User)
Closed DPW Engineering AT (Verified Official)