Thank you for your A2 Fix It request, #457186. Your request is important to us and will be prioritized and addressed based on the overall availability of city resources. Please note: If the nature of your request is urgent, such as water emergencies, please check Report a Problem - A2 Fix It for phone numbers to contact us. A2 Fix It is for non-urgent, non-emergency issues and is monitored during weekday business hours only. Your patience is appreciated.
Thank you for submitting a request relating to the condition of Nixon Road. The road was serviced for pothole repairs as a temporary solution.
Nixon Road is captured in the Capital Improvements Plan (CIP), broken into multiple phases over multiple years, as described below. For more detailed information on the upcoming Nixon Road project, visit the website at www.a2gov.org/Nixon
Phase 1 (Nixon Rd from Huron Pkwy to Bluett Rd) includes utility work (water and storm) and reconstruction of the roadway, as well as the addition of roundabouts, bike facilities, and pedestrian improvements. Anticipated start for Phase 1 is 2025.
Phase 2 (Nixon Rd from Bluett Rd to Traver Rd & Nixon Rd from Bluett to Dhu Varren) includes utility work (water and storm) and reconstruction of the roadway, as well as the addition of roundabouts, bike facilities, and pedestrian improvements. Anticipated start for Phase 2 is around 2026.
Phase 3 (Nixon Rd from Dhu Varren to M-14) includes opportunities for speed management and safety improvements for non-motorized users as part of the resurfacing. The timeline for this segment of Nixon Road is currently unknown.
2 Comments
Acknowledged City of Ann Arbor (Verified Official)
City of Ann Arbor (Verified Official)
Thank you for submitting a request relating to the condition of Nixon Road. The road was serviced for pothole repairs as a temporary solution.
Nixon Road is captured in the Capital Improvements Plan (CIP), broken into multiple phases over multiple years, as described below. For more detailed information on the upcoming Nixon Road project, visit the website at www.a2gov.org/Nixon
Phase 1 (Nixon Rd from Huron Pkwy to Bluett Rd) includes utility work (water and storm) and reconstruction of the roadway, as well as the addition of roundabouts, bike facilities, and pedestrian improvements. Anticipated start for Phase 1 is 2025.
Phase 2 (Nixon Rd from Bluett Rd to Traver Rd & Nixon Rd from Bluett to Dhu Varren) includes utility work (water and storm) and reconstruction of the roadway, as well as the addition of roundabouts, bike facilities, and pedestrian improvements. Anticipated start for Phase 2 is around 2026.
Phase 3 (Nixon Rd from Dhu Varren to M-14) includes opportunities for speed management and safety improvements for non-motorized users as part of the resurfacing. The timeline for this segment of Nixon Road is currently unknown.