Description
Countless potholes on bidirectional Nixon (passes Nixon/Dhu Varren/Green roundabout); some with length of 1 meter and rapidly worsening by the day. Extremely hazardous to swerve during the day with incoming traffic or driving on them at night without adequate lighting.
3 Comments
Acknowledged City of Ann Arbor (Verified Official)
City of Ann Arbor (Verified Official)
City of Ann Arbor (Verified Official)
Thank you for submitting a request relating to the condition of Nixon Road. The road has been serviced for pothole repairs as a temporary solution.
Nixon Road is captured in the Capital Improvements Plan (CIP), broken into multiple phases over multiple years, as described below. For more detailed information on the upcoming Nixon Road project, visit the website at www.a2gov.org/Nixon
Phase 1 (Nixon Rd from Huron Pkwy to Bluett Rd) includes utility work (water and storm) and reconstruction of the roadway, as well as the addition of roundabouts, bike facilities, and pedestrian improvements. Anticipated start for Phase 1 is 2025.
Phase 2 (Nixon Rd from Bluett Rd to Traver Rd & Nixon Rd from Bluett to Dhu Varren) includes utility work (water and storm) and reconstruction of the roadway, as well as the addition of roundabouts, bike facilities, and pedestrian improvements. Anticipated start for Phase 2 is around 2026.
Phase 3 (Nixon Rd from Dhu Varren to M-14) includes opportunities for speed management and safety improvements for non-motorized users as part of the resurfacing. The timeline for this segment of Nixon Road is currently unknown.